On the west side of Northwest Hills, the corner where RM 2222 meets Loop 360 is now a work zone. TxDOT is removing the traffic signal from the Loop 360 mainlanes at Courtyard Drive and building an underpass there. It is also rebuilding the RM 2222 interchange as a diverging diamond and adding shared-use paths and sidewalks. Crews work weekdays from 7 a.m. to 7 p.m. and on Saturdays as needed. TxDOT's most recent notice said a new eastbound RM 2222 right-turn lane to southbound Loop 360 would open as soon as Monday, November 23.
A buyer comparing homes in Northwest Hills this winter is also choosing which construction they will live next to and for how long. Each project has a posted end date. The record on this same highway suggests treating those dates as the earliest likely finish. In a Central Austin market where fewer homes are selling than a year ago, that difference is a reasonable thing to raise in a price conversation.
The West Edge Has a Late 2029 Date
According to TxDOT, the Courtyard Drive/RM 2222 project started construction in April 2026 and is expected to be finished in late 2029. Community Impact reported that crews broke ground on April 29, that the project costs $68.4 million, and that it is paid for by the City of Austin's 2016 mobility bond and TxDOT.
KXAN reported in September what the work is like for the homes closest to it. Residents of the Courtyard neighborhood, just across Loop 360 from Northwest Hills, described drilling, dust and vibration six days a week. One said a 65-foot buffer of mature trees between his backyard and the highway had been removed. The same report said the first of four phases, which covers waterlines and cliff excavation, is expected to last until summer 2027. TxDOT told KXAN it plans to repair a damaged silt fence, put up a temporary fence during the waterline work, and later build a permanent privacy fence near the right-of-way line.
Those details describe life right along the construction line. Most Northwest Hills homes are farther away. For them, the effect falls on any daily drive that passes through RM 2222 at Loop 360, which will stay a work zone for as long as the project runs.
The Westlake Project Shows How the Dates Move
The best guide to how long Courtyard/RM 2222 will take is the first Loop 360 project, at Westlake Drive and Cedar Street. That project began in June 2022, and in 2022 KUT reported TxDOT's estimate that it would take about three years. TxDOT's project page now gives late 2026 for completion, weather permitting. That works out to roughly four and a half years against an original estimate of three.
When the program was announced in 2022, TxDOT told Community Impact that each of the five intersection projects would take two to three years in total, depending on weather and funding. The Courtyard/RM 2222 schedule already runs about three and a half years, from April 2026 to late 2029. If it slips the way the Westlake project did, the RM 2222 corner could still be under construction well into 2030.
The math matters to a buyer for a simple reason. A home bought this winter on a street that uses the 2222 interchange will spend roughly the first three years of ownership beside an active work zone, and the Westlake record suggests it could be longer. The finished project has real value: no mainlane signal at Courtyard, a diverging diamond at 2222, and new paths. A buyer collects that value only after waiting out the construction.
The North Edge Finishes Sooner
Along the neighborhood's north side, the City of Austin is rebuilding Spicewood Springs Road from Loop 360 to Mesa Drive. The project has $31 million from the 2016 Mobility Bond. Construction began in December 2023. This project has slipped too. The city's August 11 update said weather delays in spring and early summer 2026 pushed substantial completion to summer 2027. It also said work on shared-use paths along both sides would begin in September, with rain gardens and lane paving continuing through the fall.
The finished road has two lanes in each direction, a raised median with left-turn bays, a shared-use path on both sides and new stormwater facilities. Measured against a purchase this winter, the north edge is about two to three years ahead of the west edge. Its remaining work is mostly finishing work, and the city has already shown how far behind schedule it is.
Where Spicewood Springs Meets Loop 360, More Work Is Planned
The quiet stretch after the city finishes Spicewood Springs Road may be short at its western end. TxDOT's Lakewood Drive/Spicewood Springs Road project would remove the Loop 360 mainlane signals at those intersections, add an overpass at the cross street, and remove the signal at west Spicewood Springs Road. It was environmentally cleared in summer 2023. Construction depends on funding but could begin in 2029. As of Community Impact's October roundup, the Loop 360 program had two projects under construction and three planned.
A home near the Spicewood Springs and Loop 360 corner could therefore see the city project finish in 2027 and a TxDOT project begin about two years later. Where a home sits relative to these two corners decides how much of either project its owner sees.
| Project | Neighborhood edge | Construction start | Posted finish | Finished result |
|---|---|---|---|---|
| Loop 360 at Courtyard Drive/RM 2222 | West | April 2026 | Late 2029 | Underpass at Courtyard, diverging diamond at RM 2222, shared-use paths |
| Spicewood Springs Road, Loop 360 to Mesa Drive | North | December 2023 | Summer 2027 | Two lanes each way, raised median, paths on both sides, stormwater facilities |
| Loop 360 at Lakewood Drive/Spicewood Springs Road | Northwest corner | As early as 2029, depending on funding | Not scheduled | Mainlane signals removed, overpass at the cross street |
| Loop 360 at Westlake Drive/Cedar Street, for comparison | Outside the neighborhood | June 2022 | Late 2026, against an early estimate of about three years | Mainlanes routed under the cross streets |
How Construction Timelines Affect Price Right Now
Community Impact's latest report charts each ZIP in its nine-ZIP Central Austin coverage area, 78731 among them, and states its headline figures for that area as a whole, based on Unlock MLS data. In October 2026, that area recorded 146 closed sales, down 17.5% from October 2025. The median price for October 2026 was $825,000, compared with $894,000 in October 2025. Homes averaged 62 days on market in October 2026, down from 78 a year earlier.
Together, those figures show fewer sales at lower prices, with the homes that do sell moving faster than last year. That points to buyers who will act on homes priced correctly and pass on the rest. Construction is one of the things buyers in this market are pricing. A seller near the 2222 interchange is competing with similar houses farther from the work, and all of them homes show up under the same neighborhood median.
These projects should also be priced in years. A buyer can count how many years of work sit between a given address and the finished road. For the RM 2222 edge, use late 2029 as the earliest end date and the Westlake record as the likely range. For the north edge, the count is shorter, apart from the corner where the Lakewood/Spicewood project may start in 2029. Then add what the address gets when the work is done: new paths, fewer signals, a Spicewood Springs Road with two lanes each way and a raised median. A buyer who plans to own for ten years has a different trade-off than one who expects to move in four.
The practical step costs only time. Before your option period ends, drive the route to the property at the hours you would actually use it, and walk the street when crews are working, weekdays between 7 a.m. and 7 p.m. Our option period guide covers what that window is for. Owners near these edges who want to know how buyers are likely to see their address can start with a home valuation.
FAQ
Which Northwest Hills roads are under construction right now? Loop 360 at Courtyard Drive and RM 2222 on the west edge, with a late 2029 finish posted, and Spicewood Springs Road from Loop 360 to Mesa Drive on the north edge, with a summer 2027 finish posted.
Is the Loop 360 work at Lakewood Drive and Spicewood Springs scheduled? No. It is environmentally cleared but depends on funding, and TxDOT says construction could begin in 2029.
What will the RM 2222 interchange look like when the work is done? TxDOT's plan has a diverging diamond interchange at RM 2222, an underpass at Courtyard Drive that removes the mainlane signal there, and new shared-use paths and sidewalks.
If you're weighing a Northwest Hills home on the west or north edge and want help judging how the construction calendar should affect your offer, The Agency Austin - Noa Levy can review the specific street with you and estimate the years of work against the price. Let's Connect.